2 Trenchard Place Framing
The basement and main floor are framed and we're ready to install the second-floor system.
The basement and main floor are framed and we're ready to install the second-floor system.
Here we see the view of 2 Trenchard Place just prior to the framing of the home about to begin. By the end of next week, the main floor will be in place.
Here we can see the backyards being created for 2, 6, and 10 Trenchard Pl.
Footings are poured.
Have plans, waiting for blasting to complete.
Blasting is now complete on this lot.
Application for building permit.
We now have the building permit for this home.
We are underway forming for the footings.
Footings got poured Dec 6/17